VIRUS SHAKES “REAL ESTATE” FOUNDATION

The Real Estate sector in India has been experiencing a downturn for quite some time. Severe liquidity crunch has plagued this sector and so have policy reforms, legislations and structural changes. These issues were merely the tip of the iceberg, as the Covid – 19 virus opened up a new front for the real estate sector.

Propelled by the burgeoning crisis,  the Confederation of Real Estate Developers Association of India (“CREDAI”) requested the  Ministry of Housing and Urban Affairs to include Covid -19 as a condition of force majeure  under Section 6 of the Real Estate (Regulation and Development) Act, 2016 (“RERA”) and that loans by real estate developers should not be classified as Non-Performing Assets in case of default on interest or principal repayment.

Force Majeure under RERA

 

Section 6 of RERA provides that if an event of force majeure (i.e. a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project) occurs, then on an application made by the promoter, the authority after considering the facts of the particular case (including that there was no default on the part of the promoter) can extend the registration for not more than one year.

It can be argued that Covid – 19 could possibly be included in “any other calamity caused by nature” in the explanation to the section. It is pertinent to note that Ministry of Finance, Department of Expenditure Procurement and Policy decision vide its office memorandum dated 19th February, 2020 clarified that the disruption of the supply chain as result of the spread of corona virus should be considered as a case of “natural calamity” and force majeure clause may be invoked.

The above section merely enjoins a delay in the performance of the contract and does not release the developer from its contractual obligations. The above section also makes it abundantly clear that facts of each case would be considered separately, and decisions taken. The period of extension in the case of Covid – 19 could possibly be not more that 3 to 4 months.

Various remedial steps taken by statutory and regulatory authorities to alleviate the difficulties of the Real Estate Sector

 

Ø The Maharashtra Real Estate Regulatory Authority vide an Order dated 2nd April, 2020 inter alia relying on section 6 of RERA, extended the period of validity for registration of MahaRERA Registered projects where completion date, revised completion date or extended completion date expires on or after 15th March 2020 by three months. Further, the time limits of all the statutory compliances, which were due in March / April / May was also extended to June 30, 2020.

Ø The Karnataka Real Estate Regulatory Authority vide a circular dated 4th April, 2020 extended the period of validity for registration of K-RERA Registered projects where completion date (including revised completion date) expires on or after 15th March 2020 by three months. Further, the time limits of all the statutory compliances, which were due in March / April / May was also extended to June 30, 2020.

Ø The Uttar Pradesh Real Estate Regulatory Authority on 14th April, 2020 has decided to extend by three months the date of completion of the projects where the date of completion is between March 15, 2020 and December 31, 2020.

Ø The Reserve Bank of India (“RBI”) vide a press release dated 27th March, 2020 has directed all commercial banks (including regional rural banks, small finance banks and local area banks), co-operative banks, all-India Financial Institutions, and NBFCs (including housing finance companies and micro-finance institutions) to allow a moratorium of three months on payment of instalments in respect of all term loans outstanding as on March 1, 2020. Further, in respect of working capital facilities sanctioned in the form of cash credit/overdraft, lending institutions have been permitted to allow a deferment of three months on payment of interest in respect of all such facilities outstanding as on March 1, 2020. It has also been clarified that moratorium/deferment provided will not result in asset classification downgrade.

As per the statement of the Governor (RBI) dated 17th April, 2020, it has been decided that in respect of all accounts for which lending institutions decide to grant moratorium or deferment, and which were standard as on March 1, 2020, the 90-day NPA norm will exclude the moratorium period. Further, the RBI allowed non-bank financial companies to extend the date for commencement of commercial operations (DCCO) for loans given to commercial real estate by additional one year,  over and above the one-year extension permitted in normal course, without considering it as restructuring. Banks had been directed to provide similar relief earlier.

Ø The Securities Exchange Board of India vide a circular dated 23rd March, 2020 has extended the due date for regulatory filings and compliances for Real Estate Investment Trusts and Infrastructure Investment Trusts for the period ending March 31, 2020 by one  month  over  and  above  the  timelines,  prescribed  under SEBI  (Infrastructure Investment  Trusts)  Regulations,  2014 (InvIT  Regulations) and  SEBI  (Real  estate Investment  Trusts)  Regulations,  2014 (REIT  Regulations) and  circulars  issued thereunder.

Relaxation on Construction activities

 

By an Order dated 15th April, 2020, the Ministry of Home Affairs has issued detailed guidelines for allowing certain additional activities to be undertaken from 20th Aril, 2020 in non – containment zones (containment zones are required to be demarcated by the respective States and Union Territories) across India, subject to all preparatory arrangements with regard to social distancing being implemented. One of these additional activities include certain construction activities which are as follows:

Ø Construction of roads,  irrigation    projects,   buildings   and  all  kinds  of industrial projects,  including   MSMEs,  in  rural  areas,  i.e.,   outside the limits  of municipal corporations   and municipalities;    and  all  kinds  of projects in industrial  estates.

Ø Construction of renewable energy projects.

Ø Continuation of works  in  construction   projects,  within  the limits  of municipal corporations and municipalities,  where workers  are available   on site and  no workers are required  to be brought in  from outside  (in  situ  construction).

Each State and Union Territory in the country will decide in which areas and to what extent the above activities can be allowed. However, this may relieve some pressure from the real estate sector. It remains to be seen whether real estate hotspots like Mumbai, Delhi and Bangalore will be permitted to allow construction activities considering that they are Covid-19 hotspots as well.

As can be seen from the above discussion, the situation with respect to Covid -19  is dynamic, and the real estate sector paradigm is bound to change as a result. Therefore, we will keep you updated in case of any further decisions, measures, notifications by the Government and other authorities with respect to the real estate sector.

 

We trust that the above update is helpful for you. If you require any further clarifications, please feel free to contact us.

Zerick Dastur <zerick@zdlegal.com>

IMPACT OF THE COVID-19 PANDEMIC ON COMMERCIAL AGREEMENTS

IMPACT OF THE COVID-19 PANDEMIC ON COMMERCIAL AGREEMENTS AND LATEST GOVERNMENT NOTIFICATIONS RELATING THERETO

As you are all aware, the world has been gripped by the outbreak of the COVID-19 epidemic which has been declared by the World Health Organization as a global pandemic. This has drastically affected the performance of many commercial contracts and resulted in many infrastructure projects coming to a sudden halt. In the present economic scenario, the concepts of force majeure and frustration of contract have gained significant importance.

Force Majeure clauses and their application

  1. Force Majeure clauses are provisions inserted by parties in contracts which exempt a performing party from its obligations upon the happening of certain events provided for in the clause itself. The occurrence of a force majeure event protects a party from liability for its failure to perform a contractual obligation.  These events are usually events over which a party has no control or events which could not have been reasonably foreseen by the parties at the time of entering into the contract.  Force majeure events are generally in the nature of acts of god i.e. natural calamities or man-made events i.e. wars, strikes, lock outs, change in government policy, political events etc. Whether or not a particular event can be classified as a force majeure event will depend on the terms of the force majeure clause and its interpretation.

2)    A force majeure clause is generally invoked by notifying the other party as soon as the concerned event has taken place or as soon as the performance of the obligations under the contract become impossible.  The party claiming force majeure is usually under a duty to show that it has taken all reasonable endeavours to avoid or mitigate the event and its effects. This would also largely depend on the contract between the parties and the interpretation thereof.

Consequences of invocation of Force Majeure

3)    Once a contracting party invokes the force majeure clause, the obligations of the parties under the contract will generally stand suspended entirely or partly till the event continues and a party cannot be held liable for the non-performance of its part of the contract during such period. As a result of such suspension, the timelines under the contract or the term of the contract may stand extended as required or as agreed between the parties. Many force majeure clauses also provide for termination of the contract if the force majeure event does not conclude within a period of time mentioned in the contract. Further consequences of the invocation of a force majeure clause will be subject to the contract between the parties.

Steps taken by the Government and various authorities

  1. The Ministry of Finance, Government of India has issued an Office Memorandum on February 19, 2020, in relation to the Government’s ‘Manual for Procurement of Goods, 2017’, which serves as a guideline for procurement by the Government. The Office Memorandum effectively states that the Covid-19 outbreak should be considered as a natural calamity and may be invoked as a force majeure.

  1. Similarly, Ministry of Shipping by its memorandum dated March 24, 2020, addressed to all major ports in India has ordered, that the COVID-19 pandemic may be considered as a valid ground for invoking force majeure clause on port activities and operations.  Pursuant to this, various major ports have further issued notifications in relation to the port operations.

  1. The Hon’ble Supreme Court by its order dated March 23, 2020 in exercise of its powers under Article 142 of the Constitution of India has directed all Courts, Tribunals and Authorities that the period of limitation prescribed under the various laws shall stand extended from March 15, 2020 till further orders. The order was passed taking cognizance of the peculiar situation arising out of the challenge faced by the country on account of COVID-19.

  1. SEBI also vide it’s circular dated March 19, 2020 extended the timelines for certain filings as required under the provisions of the SEBI (Listing Obligations and Disclosure Requirements) Regulations 2015 (‘LODR’) to listed entities. Further, by the said circular SEBI has exempted the Board of Directors and Audit Committee of the listed entities from observing the maximum stipulated time gap of 120 days under the LODR, between two meetings for the meetings held or proposed to be held between the period December 01, 2019 and June 30, 2020.

Frustration under Section 56 of the Indian Contract Act, 1956 (Contract Act)

8)    The concept for force majeure is not defined in any statute under the Indian Law. Force Majeure is a contractual remedy and can be invoked if a contract provides for the same. The Contract Act recognises the doctrine of frustration of contract under Section 56 which may also be relevant in the present context. Even in cases where a contract does not contain a force majeure clause, the performing party can claim for a discharge from performance of its obligations under the doctrine of frustration of contract under the section 56 if subsequent events make the contract impossible or impracticable to perform. Section 56 provides that an agreement to do an act which, after the contract is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful.

9)    It is a settled position of law that in order to claim termination of a contract on the grounds of frustration, the party seeking reliefs must show that the events or circumstances due to which the contract has become impossible, must be so fundamental as to be regarded by law as striking at the root of the contract. The following well settled principles need to be borne in mind while claiming relief of frustration under Section 56 of the Contract Act:

(a)  The party claiming frustration must show that concerned event or change of circumstance totally upsets the very foundation upon which the parties rested their bargain such that the promisor finds it impossible to do the act which he promised to do.

(b)  The term “impossible” used in Section 56 of the Contract Act has not been used in the sense of physical or literal impossibility but also includes situations where it becomes impracticable to perform the contract.

(c)   Once it is proved that there is frustration, a dissolution of a contract occurs and both parties are discharged from their future obligations under the contract.

(d)  If the intervening change or circumstance was contemplated by the parties at the time of entering into the contract, then the contract would stand despite the occurrence of such circumstance and no relief of frustration will apply.

10) In view of the prevailing situation, it is important for companies to carry out a detailed review of its contracts and analyse the rights and obligations of the parties, performance of which is likely to be affected.  The review must specifically include (but not limited to) analysis of the clauses on termination, force majeure, compensation, governing law and dispute resolution. A detailed review of its operations and the likely effects and risks attached to suspension of its operations must be undertaken.

We trust that the above analysis is helpful for you to assess the legal impact of the current scenario on your business and operations and accordingly, enable you to take appropriate commercial decisions. If you require any further clarifications, please feel free to contact us. We will update you in case of any further decisions, measures, notifications by the Government and other authorities in this regard.

Zerick Dastur, Advocates and Solicitors